Industry Spotlight
Limiting liability under construction contracts
Most people involved in the construction industry will be well aware of the proposed review of the NZS 3910 construction contract.[1] The intention is to review and amend NZS 3910 in order to align it with recent law changes, and make it more responsive to the practical requirements of the industry.
The key issues of limitation of liability and indemnity have been tabled for consideration as part of that review. In a sector-wide survey conducted by Standards New Zealand in early 2021, 69.5% of respondents either agreed or strongly agreed that the ideal outcome for a revision of NZS 3910 would be a contract which included optional caps on liability and indemnity.[2]
The clauses
Clauses which create indemnities or limit liability are included in commercial contracts as a way of allocating risk between the parties. Limitation clauses allocate risk by either limiting a party's obligations under the contract, or limiting the availability of remedies where the contract is breached. Indemnity clauses allocate risk by specifying which party will be liable in the event that certain losses are incurred. This means that even if 'Party A' has to pay the upfront costs of that event, 'Party B' will be obliged to repay them.
Under NZS 3910 the contractor gives wide indemnities under clause 7. In some cases, under clause 10, the contractor also agrees to pay liquidated damages in the event of late completion.
There is no limitation or liability cap included within either section. Nor is there an exclusion for indirect or consequential loss. It is rare to see a commercial contract without such caps or exclusions. The introduction of caps and exclusions to NZS 3910 has been discussed for some time, and is increasingly being sought by contractors.[3]
Changes proposed
Adjustment to the standard terms has the potential to significantly alter the allocation of risk under the contract and should be confirmed only after very careful consideration of the ramifications involved.
In particular, parties should bear in mind the legal requirements which must be met for a limitation of liability clause to be enforceable:
-
A party who wishes to rely on such a clause would need to show that it is intended to cover the relevant obligation or liability.[4] In every case, it will be a question of the construction of the contract as a whole.
-
Clear words will be necessary before a court would be willing to conclude that a party did intend to limit or abandon its remedies in this way.[5]
-
This means that the more restrictive the exclusion or limitation clause, the clearer the wording will need to be in order for it to have effect.
Deliberate breach?
An issue which can arise is whether a limitation or exclusion clause is intended to apply where the party deliberately breached the contract. This might become relevant in the context of a construction dispute if, for example, the contractor, in breach of contract, deliberately withheld documentation necessary for code compliance certification, and then sought to rely on a limitation clause to limit a claim for damages arising from that breach.
To address that issue, the court (or arbitrator) would be primarily focused upon the interpretation of the limitation or exclusion clause in question.
A recent High Court decision typified the approach taken in England and Wales. In Mott MacDonald Ltd v Trant Engineering Ltd (TEL), the Ministry of Defence had engaged TEL to construct a new power station.[6] TEL then engaged Mott MacDonald to provide consultancy services. When a dispute developed, the parties entered into a settlement and services agreement (Agreement), designed to resolve their existing dispute and to clarify each party's ongoing obligations.
The Agreement included a limitation clause. It provided that Mott MacDonald would only be liable to pay compensation to TEL under or in connection with the Agreement if a breach of the Agreement by Mott MacDonald was established. It also limited Mott MacDonald's total liability, including "in contract or in tort, in negligence or for breach of statutory duty or otherwise" to £500,000, and provided that it would have no liability for indirect, special or consequential loss.
The parties' working relationship did not improve. Mott MacDonald sued TEL, seeking payment of around £1.7m in fees. In response, TEL said that Mott MacDonald had "fundamentally, deliberately and wilfully" breached its obligations under the Agreement, including by:
-
refusing to complete the required design deliverables;
-
refusing to provide TEL with native data files and detailed calculations it had created; and
-
failing to carry out independent reviews of its design.
TEL said that the limitation clause therefore did not apply. It claimed around £5 million in losses.
Mott MacDonald applied for summary judgment to determine whether TEL's claim was subject to the limitation and exclusion clause.
The Court said that the limitation and exclusion clause applied, whether or not the breaches were deliberate, as alleged. This was because the relevant clauses were:
-
in clear terms and capable, when read naturally, of applying to the alleged breaches;
-
contained in a bespoke agreement entered into between two commercial entities; and
-
designed both to resolve an existing dispute and set out a regime governing further dealings with a view to avoiding renewed disputes.
To adopt TEL's preferred interpretation in those circumstances would amount to implying exceptions into the clear terms of the contract's limitation clauses. There was no basis for doing so.
In our view, the same result would be likely in the New Zealand Courts.
Conclusion
The introduction of limitation or exclusion clauses and caps on liability can have a profound impact on the rights and remedies available under the contract, and will alter the risk profile of a project significantly. It is worth taking legal advice before considering such changes, to ensure that the parties' intentions are captured accurately, and are legally enforceable.
Two key points to bear in mind:
-
If such clauses are to be included, the parties, especially principals, should carefully consider their scope. It may be necessary to specify that the limitations or caps will not apply in certain circumstances, for example, where there are deliberate breaches, insured losses, breaches of confidentiality, or intellectual property obligations.
-
Clarity will go a long way towards avoiding a dispute. Use specific language to clearly state which losses are recoverable, and which are not.
Contributors: Michael Taylor & Joanna Trezise